Concrete Calculator

Enter your slab, footing, or column dimensions below to calculate exactly how much concrete you need, either in cubic yards for ready-mix delivery or in bags (40, 60, or 80 lb) if you’re mixing by hand. The calculator automatically adds a waste buffer so you don’t come up short mid-pour.

Volume
33.3 cu ft
Ready-mix (incl. waste)
1.36 cu yd
80 lb bags needed
62
Estimated cost
—
Bags needed by bag size
Bag sizeBags needed
40 lb123
50 lb98
60 lb82
80 lb62

Includes a 10% waste buffer. Ready-mix concrete is typically sold in quarter- or half-yard increments. Round up when ordering.

How to Calculate How Much Concrete You Need

Whether you’re pouring a patio, a fence post footing, or a support column, the math behind every concrete project comes down to the same four steps.

Post footings are the case where the concrete volume depends on a count you have not made yet. Post spacing sets how many holes there are, and that follows from the fence layout rather than from the concrete: the fence calculator works out posts, rails and pickets from the run length first.

Step 1: Measure Your Project Dimensions

For a slab or footing, measure the length, width, and thickness in inches or feet. For a round column or post hole, measure the diameter (or radius) and the height or depth instead.

Most residential slabs (patios, walkways, and shed pads) are poured 4 inches thick. Driveways typically need 4 to 6 inches, and anything supporting a vehicle heavier than a standard car (RVs, trucks, equipment) should go to 6 inches or more.

Step 2: Calculate the Volume

For a rectangular slab or footing:

Volume (cubic feet) = Length (ft) × Width (ft) × Thickness (ft)

For a round column or post:

Volume (cubic feet) = π × Radius² × Height (ft)

Example: A 10 ft × 10 ft patio slab at 4 inches thick.

  1. Convert thickness to feet: 4 ÷ 12 = 0.33 ft
  2. Volume = 10 × 10 × 0.33 = 33.3 cubic feet

Step 3: Convert to Cubic Yards

Ready-mix concrete is sold by the cubic yard, not the cubic foot. There are 27 cubic feet in a cubic yard, so divide your total by 27.

33.3 ÷ 27 = 1.23 cubic yards

Step 4: Add a Waste Factor

Uneven subgrade, spillage, and over-excavation typically use up 5–10% more concrete than the clean geometry math predicts. Add 10% before you order or buy bags. It’s far cheaper than a second delivery trip.

1.23 × 1.10 = 1.36 cubic yards

Since most ready-mix suppliers sell in quarter- or half-yard increments (and charge a short-load fee for small orders), round up to 1.5 cubic yards for this example.

How Many Bags of Concrete Do I Need?

For smaller pours, bagged mix is usually more practical than ordering a truck. Each bag lists its dry weight, but what matters for this calculation is its yield, the volume it makes once mixed with water:

Bag Size Yield (cubic feet) Bags per Cubic Yard
40 lb 0.30 90
50 lb 0.375 72
60 lb 0.45 60
80 lb 0.60 45

Continuing the example above: 33.3 cubic feet, plus 10% waste = 36.6 cubic feet.

36.6 ÷ 0.60 (80 lb bag yield) = 61 bags → round up to 62 bags of 80 lb mix.

One thing bagged concrete is not for: filling the cores of a block wall. Core fill is a separate product with a much higher slump, and reaching for a bag of concrete mix instead is a common and expensive substitution. The mortar, grout and core fill guide covers why the three products are not interchangeable.

Bagged Concrete vs. Ready-Mix Delivery

As a rule of thumb: under about 1 cubic yard, bagged concrete is usually cheaper and easier to manage yourself. Once a project crosses 1.5–2 cubic yards, ready-mix delivery is typically the better deal. Bagged concrete works out to roughly double the cost per cubic yard once you account for the number of bags needed, and hand-mixing 60+ bags is a full day of labor most people would rather avoid.

In 2026, ready-mix concrete costs approximately $120–$180 per cubic yard delivered (national average around $150), depending on your region, the PSI strength you need, and delivery distance. Standard 3,000 PSI mix covers most residential slabs; garage floors and heavy-load areas typically call for 4,000 PSI or higher.

What You Have to Specify When You Order Ready-Mix

Bagged concrete comes as one product. Ready-mix does not: the plant needs you to state what you want, and the defaults you get by saying nothing are not always right for the job.

Strength. Quoted in PSI at 28 days. Residential patios, walkways and shed pads normally use 3,000 PSI. Driveways and garage floors are usually specified at 3,500 to 4,000, and anything exposed to de-icing salts wants the higher figure with air entrainment. Strength is cheap relative to the cost of replacing a failed slab, so this is a poor place to economise.

Slump. How far the mix settles under its own weight, a proxy for how wet it is. Four inches is a typical slab slump. Asking for a wetter mix makes placing easier and the finished concrete weaker, because the extra water raises the water-to-cement ratio. If the crew wants it wetter on site, that is what a plasticiser is for, not a hose.

Air entrainment. Deliberate microscopic bubbles that give freezing water somewhere to expand into. Anything exposed to freeze-thaw needs it. It is not optional in cold climates and it cannot be added usefully after the truck arrives.

Three charges catch people out on a first order. Short-load fees apply below roughly 3 or 4 cubic yards and can make a slightly larger order cheaper than a small one. Standby time is billed once the truck waits beyond an allowance, commonly 5 to 7 minutes per cubic yard, so the site needs to be ready before it arrives. And the washout has to happen somewhere: agree where before the truck is on site, because concrete rinse water is caustic and cannot go into a drain or a planting bed.

Frequently Asked Questions

How thick should a concrete slab be?
Most patios, walkways, and shed pads use a 4-inch slab. Driveways typically need 4 to 6 inches, and anything that will support trucks, RVs, or heavy equipment should be poured at 6 inches or thicker.
Do I need rebar in my concrete slab?
It depends on the slab's thickness, soil conditions, and load. Many standard 4-inch patios use wire mesh or no reinforcement at all, but driveways, slabs on expansive soil, and anything load-bearing typically call for rebar. Use our rebar calculator to estimate material, and consult a structural engineer for load-bearing applications.
How long does concrete take to cure?
Concrete is typically safe to walk on after 24–48 hours and can handle light vehicle traffic after about 7 days. It reaches close to its full rated strength at 28 days, which is why 28-day strength is the industry-standard benchmark for testing.
Can I pour concrete in cold weather?
Avoid pouring if temperatures are expected to drop below 40°F within 24 hours of the pour, unless you're using insulating blankets, a heated enclosure, or a cold-weather admixture. Cold temperatures slow curing significantly and can weaken the final slab if the mix freezes before it sets.
Is it cheaper to buy bags or order a truck?
For projects under about 1 cubic yard, bagged concrete is usually cheaper and more practical. Above 1.5–2 cubic yards, ready-mix delivery typically costs less per cubic yard and saves a significant amount of labor.

Estimates on this page are for planning purposes. Actual material needs can vary based on subgrade conditions, mix design, and site-specific factors. Confirm quantities with your supplier before ordering, and consult a licensed contractor or structural engineer for any load-bearing or structural application.

Written by: The CubedCalc Team. We research and fact-check every calculator using manufacturer specs, building codes, and industry references. We are not licensed contractors or engineers; always verify structural or code-critical numbers with a qualified professional.